Develops and leases data center space supported by private power and site infrastructure for hyperscalers, cloud providers and other large compute users.
10-K for FY2025, filed Mar 30, 2026Fermi Inc. (“Fermi,” “we,” “us,” or “our”) exists to power the artificial intelligence needs of tomorrow. We are building a private power…View ↗
Our strategy is anchored by Project Matador, a hyperscale power and AI infrastructure campus in the Texas Panhandle region secured by our…View ↗
We are developing a powered campus model in which we control a 5,236-acre site in Carson County, Texas under a 99-year ground lease (the…View ↗
Our target customers are hyperscale and other large-scale compute users, including cloud service providers, AI infrastructure operators…View ↗
No revenue reported yet.
10-K for FY2025, filed Mar 30, 2026
Fermi targets hyperscalers and other large compute users, including cloud service providers, AI infrastructure operators and chipmakers, plus enterprises and governmental or quasi-governmental entities. Planned customers would lease on-site facilities and power capacity.
10-K for FY2025, filed Mar 30, 2026
10-Q for Q3 FY2026, filed Nov 12, 2026
−$141.6MView ↗
8-K, filed Nov 12, 2026
$200 million prepayment agreement: Provides for substantial upfront customer funding in connection with the proposed 600 MW development.View ↗
8-K, filed Aug 31, 2026
On August 12, 2026, the Company announced that independent director Lee McIntire had been appointed as Chief Executive Officer of the…View ↗